Project Management Professional (PMP) Exam Practice – Question0475

During a project steering committee meeting, the project manager reports that a formerly supportive key team member has become resistant to and negative about changes. Where should this information be captured?


A.
Responsible, accountable, consult, and inform (RACI) matrix
B. Stakeholders engagement assessment matrix
C. Risk register and issue log
D. Work performance reports

Correct Answer: B