Project Management Professional (PMP) Exam Practice – Question0477

A project manager must provide cost estimates to stakeholders. What should the project manager present to avoid unreasonable cuts in the budget that will undermine the project?


A.
High-level costs summarized by resource
B. Bottom-up costs as the basis for the estimate
C. Cost estimates as per historical data and other variables
D. Cost estimates using expert judgement

Correct Answer: C