A procurement manager needs to determine what type of contract to use for a construction project using a new supplier. What type of contract incorporates the highest risk?


A.
Cost plus award fee (CPAF)
B. Cost plus incentive fee (CPIF)
C. Cost plus percentage of cost (CPPC)
D. Cost plus fixed fee (CPFF)

Correct Answer: C