Project Management Professional (PMP) Exam Practice – Question0481

A project manager develops a projects risk breakdown structure (RBS) divided into four categories. The team identifies a quality problem with one of the project deliverables.
In what category should this risk be included?


A.
Organizational
B. Project management
C. Technical
D. External

Correct Answer: C