Project Management Professional (PMP) Exam Practice – Question0482

Currently, a project has a considerable list of risks that can significantly impact the project deliverables. What should the project manager do to prioritize the risks?


A.
Sort the risks according to their impact.
B. Perform a qualitative risk analysis.
C. Identify what risks have the highest probability.
D. Perform a quantitative risk analysis.

Correct Answer: B