Project Management Professional (PMP) Exam Practice – Question0485

A project manager developed a project management plan for a team composed of members based in three countries. The project manager assumed a 40-hour work week for all team members. However, during project execution, the project manager learns that
one countrys team members work a 35-hour week.

Where should this information have been captured?


A.
Organizational process assets
B. Enterprise environmental factors
C. Legal requirements documentation
D. Responsible, accountable, consult, and inform (RACI) chart

Correct Answer: B