A project manager developed a project management plan for a team composed of members based in three countries. The project manager assumed a 40-hour work week for all team members. However, during project execution, the project manager learns that
one countrys team members work a 35-hour week.
one countrys team members work a 35-hour week.
Where should this information have been captured?
A. Organizational process assets
B. Enterprise environmental factors
C. Legal requirements documentation
D. Responsible, accountable, consult, and inform (RACI) chart