Project Management Professional (PMP) Exam Practice – Question0489

While developing the responsible, accountable, consult, and inform (RACI) matrix, the project manager identifies that a project work package does not have a defined owner. What should the project manager do?


A.
Directly assume the responsibility.
B. Consult the resource and work breakdown structures to verify who is accountable.
C. Assign an owner based on who has the fewest assigned responsibilities.
D. Consult the project sponsor.

Correct Answer: B