Project Management Professional (PMP) Exam Practice – Question0490

A team member assigned to an activity with two days total float takes a one-week emergency leave. This will impact not only that activity, but the entire project. There are no available resources to assign to this activity.
What should the project manager do next?


A.
Update the issue log, and review the risk register for the risk response.
B. Request an external resource.
C. Move a resource from an activity that has more float.
D. Issue a change request to the change control board (CCB) to revise the project schedule.

Correct Answer: A