Project Management Professional (PMP) Exam Practice – Question0500

During the annual project-planning workshop, the human resource director requests the development of a new employee-leave application system. The project management office (PMO) is responsible for following up on this request.
What should the PMO do next?


A.
Check available systems on the market.
B. Determine the available budget.
C. Obtain a project statement of work (SOW).
D. Create a project management plan.

Correct Answer: C