Project Management Professional (PMP) Exam Practice – Question0501

The communications technology being applied in a project was tested in simulated environments but never in actual projects. This lack of experience with the technology must be addressed in detail.
Which of the following strategies should be used in the project's planning process?


A.
Provide a status update to senior management.
B. Update the project scope if the project grows more complex.
C. Mitigate the risk by conducting a pilot.
D. Exploit the threat by using an alternative technology.

Correct Answer: C