Project Management Professional (PMP) Exam Practice – Question0502

A company is using Lean Six Sigma methodology on a project. Midway through the project, an external Lean consultant is invited to conduct an audit to ensure that the methodology is being properly applied.
Which process is being employed?


A.
Manage Quality
B. Control Quality
C. Perform Qualitative Risk Analysis
D. Plan Quality Management

Correct Answer: D