Project Management Professional (PMP) Exam Practice – Question0503

During business process mapping, an analyst discovers that some business activities that were not a part of the original project scope may need to be included. The analyst documents these activities and informs the project manager.
What should the project manager do?


A.
Update the project management plan.
B. Perform a risk assessment.
C. Review the resource management plan.

D. Update the issue log.

Correct Answer: A