Project Management Professional (PMP) Exam Practice – Question0504

A project must be simultaneously implemented in two countries with a time-zone difference of 11 hours. The project manager must determine a mutually convenient time to provide stakeholders with information on the project's schedule, cost, and performance
progress.
What should the project manager use to determine this?


A.
Communication requirements analysis
B. Asynchronous brainstorming
C. Expert judgment
D. Meeting planning skills

Correct Answer: A