Project Management Professional (PMP) Exam Practice – Question0505

A project manager is in the final stage of cost estimation. A colleague informs the project manager that costs must be increased, as the client requested additional scope.
What should the project manager consider before proceeding?


A.
Project funding requirements
B. Organizational processes
C. Agreements
D. Project charter

Correct Answer: B