Project Management Professional (PMP) Exam Practice – Question0507

An ongoing cross-functional project has team members located in several different countries, and stakeholders who provide insufficient support. How can the project manager improve this situation?


A.
Conduct cross-cultural team building activities, and assess the results.
B. Consult the communications management plan, and update the responsibility assignment matrix (RAM).
C. Prepare a change request to colocate, and more closely manage, the team.
D. Review the stakeholder register, and update the stakeholders engagement assessment matrix.

Correct Answer: B