A project manager is assigned to a project that is in progress. In which of the following documents would a new project manager find information regarding the scope baseline?
A. Project management plan
B. Project scope statement
C. Project charter
D. Project requirements
A. Project management plan
B. Project scope statement
C. Project charter
D. Project requirements