Project Management Professional (PMP) Exam Practice – Question0509

A project manager is working with the project sponsor to write the project charter for a joint venture project. The project manager's company and the sponsor's company worked together previously, but had several projects cancelled due to opposing objectives.
Therefore, the project sponsor wants to ensure that conflicts of interest are avoided.
What should the project manager do?


A.
Obtain approval from the sponsor to use relevant organizational process assets from previous projects.
B. Conduct a benefits analysis with identified stakeholders to validate project alignment.
C. Ensure that bid documents include how conflicts of interest will be resolved during project execution.
D. Perform frequent measurement and tracking techniques to ensure that conflicts of interest are identified early.

Correct Answer: D