At project inception, market demands result in a shift in the client's organizational strategy. Upon learning this, the project manager immediately requests a meeting with the project team and project sponsor.
In preparation for this meeting, what should the project manager analyze and evaluate?
A. Approved scope statement
B. Business case
C. Enterprise environmental factors
D. Project management plan