Project Management Professional (PMP) Exam Practice – Question0517

A project manager leading the implementation of a company's new financial system needs to evaluate the system's quality. What can the project manager use to understand the project's quality metrics and policies?


A.
Quality control measurements
B. Process analysis
C. Quality management plan
D. Quality audits

Correct Answer: C