Project Management Professional (PMP) Exam Practice – Question0518

A project manager realizes that a new government regulation affects the current project, and to be compliant with the new law, the scope of the project should be changed. The team is now analyzing the impact on the schedule and budget.
Which tool or technique should the project manager have considered before this issue occurred?


A.
Stakeholder register
B. Stakeholder analysis
C. Risk management plan
D. Risk register

Correct Answer: C