Due to stakeholders schedule commitments, an expansion project is being fast tracked. Some construction activities must be initiated before all basic scope specifications are completely developed.
What type of construction contract should the procurement manager negotiate?


A.
Cost plus fixed fee (CPFF)
B. Cost plus incentive fee (CPIF)
C. Firm fixed price (FFP)
D. Fixed price incentive fee (FPIF)

Correct Answer: B