Project Management Professional (PMP) Exam Practice – Question0520

A project manager is developing a project risk register. What tool or technique should the project manager use to generate a list of all possible project risks?


A.
Monte Carlo simulation
B. Tornado diagram
C. Brainstorming
D. Sensitivity analysis

Correct Answer: C