A new warehouse facility is under construction. The project manager knows that increasing the teams training will result in a lower defect ratio.
What should the project manager do next?
A. Introduce a training program.
B. Update the resource management plan.
C. Increase quality control reviews.
D. Add training costs to the budget.
What should the project manager do next?
A. Introduce a training program.
B. Update the resource management plan.
C. Increase quality control reviews.
D. Add training costs to the budget.