Project Management Professional (PMP) Exam Practice – Question0526

A project manager is concerned about variations in the requirements-gathering process. What should the project manager do to address quality concerns during this process?


A.
Review the work performance reports to identify areas for improvement
B. Implement the Six Sigma approach to evaluate improvement opportunities
C. Perform quality control on all requirements process deliverables
D. Add additional resources to the requirements-gathering process

Correct Answer: B