Project Management Professional (PMP) Exam Practice – Question0527

A project manager is creating the communications management plan for a critical project. It is quickly identified that key stakeholders have hidden agendas and are waiting for the right moment to complain about an issue.
What should the project manager do to expose this in a timely manner?


A.
Formally involve these stakeholders in the deliverables approval process
B. Ask these stakeholders to officially share their project expectations
C. Include these stakeholders in project monitoring activities
D. Monitor these stakeholders participation during project execution, and engage them frequently

Correct Answer: B