Project Management Professional (PMP) Exam Practice – Question0528

A project manager is working on a project involving stakeholders in multiple geographic locations. It soon becomes extremely difficult for everyone to be available for meetings at the same time.
What should the project manager do to make sure the project management plan is approved?


A.
Use expert judgment
B. Meet with the project sponsor to finalize the plan
C. Share the plan electronically, then follow up when needed
D. Facilitate a brainstorming session with the project team

Correct Answer: C