Project Management Professional (PMP) Exam Practice – Question0529 Enterprise environmental factors are an input to which process? A. Control Scope B. Define Scope C. Plan Scope Management D. Collect Requirements Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0528Project Management Professional (PMP) Exam Practice – Question0530