Project Management Professional (PMP) Exam Practice – Question0532

A project manager is working on a critical project for which historical data is unavailable. This may put the project at risk.
What should the project manager do?


A.
Plan project execution based on stakeholders risk appetites.
B. Develop the project management plan to identify and prioritize opportunities and threats.
C. Inform the sponsor of the risk involved, then continue with project delivery.
D. Develop a risk management plan and inform key stakeholders about the risks involved.

Correct Answer: D