A project manager is working on a project for which some requirements have not been clearly defined. The customer insists that this should not be considered a problem and the project should continue without delay.
What should the project manager do first?


A.
Meet with the team to discuss the concerns.
B. Speak with the customer to avoid the risk.
C. Log the risk in the risk register.
D. Accept the risk and start project work.

Correct Answer: B