A project manager identifies a risk and its possible impact. The project manager notifies the sponsor that sufficient budget, schedule, and other resources have been allocated to respond to the risk if it occurs.
What risk response strategy did the project manager use?
A. Avoid
B. Accept
C. Mitigate
D. Transfer
What risk response strategy did the project manager use?
A. Avoid
B. Accept
C. Mitigate
D. Transfer