Project Management Professional (PMP) Exam Practice – Question0539

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:


A.
Continuous improvement.
B. Predictive planning.
C. Progressive elaboration.
D. Quality assurance.

Correct Answer: C