Project Management Professional (PMP) Exam Practice – Question0540

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:


A.
Earned value management.
B. Enterprise environmental factors.
C. Organizational process assets.
D. Work performance information.

Correct Answer: D