Project Management Professional (PMP) Exam Practice – Question0545 An output of the Create WBS process is: A. Scope baseline. B. Change requests. C. Accepted deliverables. D. Variance analysis. Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0544Project Management Professional (PMP) Exam Practice – Question0546