Project Management Professional (PMP) Exam Practice – Question0550

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?


A.
$50
B. $100
C. $125
D. $200

Correct Answer: D

Explanation:

Explanation:
EAC=BAC/CPI and CPI=EV/AC
CPI = EV/ AC = 25/50 = 0.5
EAC = BAC/ CPI = 100/0.5 = $200