Project Management Professional (PMP) Exam Practice – Question0550 What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25? A. $50 B. $100 C. $125 D. $200 Show Answer Hide Answer Correct Answer: D Explanation: Explanation: EAC=BAC/CPI and CPI=EV/AC CPI = EV/ AC = 25/50 = 0.5 EAC = BAC/ CPI = 100/0.5 = $200 Post navigation Project Management Professional (PMP) Exam Practice – Question0549Project Management Professional (PMP) Exam Practice – Question0551