Project Management Professional (PMP) Exam Practice – Question0554 In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team? A. Performing B. Storming C. Norming D. Forming Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0553Project Management Professional (PMP) Exam Practice – Question0555