Project Management Professional (PMP) Exam Practice – Question0555

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:


A.
Acquire Project Team.
B. Plan Human Resource Management.
C. Manage Project Team.
D. Develop Project Team.

Correct Answer: A