Project Management Professional (PMP) Exam Practice – Question0558

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?


A.
Critical path method
B. Critical chain method
C. Resource leveling
D. Schedule network analysis

Correct Answer: B