Project Management Professional (PMP) Exam Practice – Question0560

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:


A.
adaptive
B. reflexive
C. predictive
D. iterative

Correct Answer: A