Project Management Professional (PMP) Exam Practice – Question0561

Variance and trend analysis is a tool and technique used in which process?


A.
Perform Qualitative Risk Analysis
B. Perform Quantitative Risk Analysis
C. Control Risks
D. Plan Risk Responses

Correct Answer: C