Project Management Professional (PMP) Exam Practice – Question0564

Analytical techniques are a tool and technique of which process in Project Procurement Management?


A.
Plan Procurement Management
B. Control Procurements
C. Conduct Procurements
D. Close Procurements

Correct Answer: C