Project Management Professional (PMP) Exam Practice – Question0567 Which Process Group includes the Manage Stakeholder Engagement process? A. Executing B. Planning C. Monitoring and Controlling D. Initiating Show Answer Hide Answer Correct Answer: A Explanation: Explanation: Reason: Control Stateholder Engagement is in the Monitoring and Control Process. Post navigation Project Management Professional (PMP) Exam Practice – Question0566Project Management Professional (PMP) Exam Practice – Question0568