Project Management Professional (PMP) Exam Practice – Question0569

A project manager requesting industry groups and consultants to recommend project intervention is relying on:


A.
Communication models.
B. Stakeholder participation.

C. Expert judgment
D. Enterprise environmental factors.

Correct Answer: C