A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A. Communication models.
B. Stakeholder participation.
C. Expert judgment
D. Enterprise environmental factors.
A. Communication models.
B. Stakeholder participation.
C. Expert judgment
D. Enterprise environmental factors.