Project Management Professional (PMP) Exam Practice – Question0572 A project manager who communicates to the project team though email is using which type of communication? A. Formal B. Informal C. Horizontal D. Unofficial Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0571Project Management Professional (PMP) Exam Practice – Question0573