Project Management Professional (PMP) Exam Practice – Question0582

When would resource leveling be applied to a schedule model?


A.
Before constraints have been identified
B. Before it has been analyzed by the critical path method
C. After it has been analyzed by the critical path method
D. After critical activities have been removed from the critical path

Correct Answer: C