Project Management Professional (PMP) Exam Practice – Question0583

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?


A.
Utilize the change control process.
B. Crash the schedule to fix the defect.
C. Leave the defect in and work around it.
D. Fast-track the remaining development.

Correct Answer: A