Project Management Professional (PMP) Exam Practice – Question0585 Which type of analysis would be used for the Plan Quality process? A. Schedule B. Checklist C. Assumption D. Cost-Benefit Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question0584Project Management Professional (PMP) Exam Practice – Question0586