Project Management Professional (PMP) Exam Practice – Question0590

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?


A.
Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline

Correct Answer: D